Optimization of the Ústí nad Orlicí - Česká Třebová railway section
| Project number: | 2000 CZ 16 P PT 002 |
| Project location: | Pardubice Region |
| The exact place of realization: | NUTS II - Severovýchod |
| Corridor: | 1, 3 |
| Project start date: | 1. June 2002 |
| Project completion date: | 1. February 2004 |
| EU financial resources: | Fond ISPA |
| Approved Project total cost: | 28,600,160 € ( 957,523,200 Kč ) |
| Approved EU contribution: | 14,300,080 € ( 457,602,560 Kč ) |
| Final beneficiary: | Railway Infrastructure Administration, state organisation (RIA) |
| National co-financing authority: | State Fund of Transport Infrastructure (SFTI) |
| Construction supervision: | Správa železniční dopravní cesty (SŽDC), Stavební správa Praha |
| Contractor: | SKANSKA ŽS a.s. |
| Detailed design contractor, author´s supervision: | SUDOP Praha a.s. |
| Supervision contractor: | Babtie Group |
| Date of project financing decision: | 7. February 2001 |
| Project approved by: | European Commission |
| Ref.No. of the decision: | 2000 CZ 16 P PT 002 |
|