European Train Control System (ETCS), Pilot project Poricany-Kolin

Project number: 2002/CZ/16/P/PT/015
Project location: Central Bohemian Region
The exact place of realization: NUTS II Střední Čechy
Corridor: 1, 3
Project start date: 14. April 2005
Project completion date: 29. September 2011
EU financial resources: Fond soudržnosti 2004 - 2006
Approved Project total cost: 9,800,000 €   ( 311,128,224 Kč )
Approved EU contribution: 7,350,000 €   ( 235,200,000 Kč )
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Construction supervision: Správa železniční dopravní cesty (SŽDC), Stavební správa Praha
Contractor: ANSALDO SIGNAL, Ansaldo Segnalamento Ferroviario S.p.A.
Detailed design contractor, author´s supervision: ANSALDO SIGNAL, Ansaldo Segnalamento Ferroviario S.p.A.
Date of project financing decision: 15. December 2003
Project approved by: European Commission
Ref.No. of the decision: DL(2003)3476