Červenka – Zábřeh na Moravě track section modernisation
| Project number: | 2004/CZ/16/C/PT/002 |
| Project location: | Olomouc Region |
| The exact place of realization: | NUTS II Střední Morava |
| Corridor: | 2, 3 |
| Project start date: | 1. August 2005 |
| Project completion date: | 1. October 2008 |
| EU financial resources: | Fond soudržnosti 2004 - 2006 |
| Approved Project total cost: | 136,569,184 € ( 3,698,000,000 Kč ) |
| Approved EU contribution: | 100,148,250 € ( 3,204,744,000 Kč ) |
| Final beneficiary: | Railway Infrastructure Administration, state organisation (RIA) |
| National co-financing authority: | State Fund of Transport Infrastructure (SFTI) |
| Construction supervision: | Správa železniční dopravní cesty, Stavební správa Olomouc |
| Contractor: | Sdružení „Koridor Červenka-Zábřeh“ (pod vedením Skanska ŽS a.s. 60%, dále Subterra a.s. 20% a Leonhard Weiss GmbH & Co. KG 20%) |
| Detailed design contractor, author´s supervision: | IKP Consulting Engineers, s.r.o. a SUDOP Brno a.s. |
| Supervision contractor: | Fram Consult a.s. |
| Date of project financing decision: | 1. August 2005 |
| Project approved by: | European Commission |
| Ref.No. of the decision: | 2004/CZ/16/C/PT/002 |
|