Brno - 1st part of storage sidings, 1st phase

Capacity details

Scope of the construction on relevant lines

  • Track No. 250 section Břeclav - Brno km 139,448 to 141,515, i.e. 2,067 km
  • Track No. 240 section Střelice - Brno km 151,910 to 153,591, i.e. 1,681k m
  • Interconnection for freight km 0,0 to 2,282, i.e. 2,282 km

Railway superstructure

  • Track type UIC 60 - 4614 m and 4348 m
  • Track type S 49 - 9 184 m and 8 192m
  • Rail type R 65, S 49 regenerate - 1 747 m and 1 704 m
  • Switches UIC 60 - 16 and 16
  • Switches S 49 - 27 and 26

Bridges and artificial structures

  • Retaining walls - 1 691 m and 942 m
  • Railway bridges reconstructed - 3 and 3
  • Railway bridges new - 9 and 9
  • Underpasses - 2 and 2
  • Road bridges - 2 and 1

Communication equipment and Long-distance track control

  • Data server - 1 and 8
  • Cameras of the closed-circuit television - 9 and 6
  • Clocks – 61 and 3
  • Equipping the long-distance track control and control system - 1 and 1
  • Secondary station RTU - 6 and 10
  • Equipping the secondary station RTU - 3 and 3

Signalling equipment

  • Operating control posts with a new station interlocking equipment electronic 3rd category - 2 and 2
  • Operating control posts with the current modified station interlocking equipment relay 3rd category - 1 and 1
  • Operating control posts with the current modified interlocking equipment 2nd category - 1 and 1
  • Electro-motor switch point machine - 73 and 54

Heavy-current equipment and contact line system

Transformer station 22/0,4

  • New - 4 and 6
  • Reconstructed - 2 and 1
  • For the feeding of signalling equipment - 1 and 1
  • For the feeding of electric switch heating - 11 and 4

Distribution station low-voltage

  • Reconstructed - 2 and 2
  • New - 7 and 2

Electric pre-heating equipment

  • TR 25/3 kV - 3 and 0
  • Pre-heating station - 10 and 0

Other equipment

  • Lighting mast 12 to 14 m - 94 and 48
  • New contact line system - 24600 m and 24500 m
  • Overhead contact line in buildings - 1 200 m and 0 m
  • Feeding line and return circuit - 19 100 m and 12 500 m
  • Adjustments of the current contact line system - 3 800 m and 1 800 m
  • Electrically heated switches - 48 and 35
  • Lighting tower 20 m - 2 and 0

Structures and roads

  • Concrete areas and roads - 34 490 m2 and 24 326 m2
  • New constructions - 367 214 m3 and 15 083 m3
  • Renovation of the current areas - 480 m2 and 243 m
  • Demolition - 18 180 m3 and 10 682 m3
  • Noise barriers - 1 410 m and 1 177 m

Energy requirement

  • Electrical energy from the distribution system of the Czech Railways - 5 540 MWh/year and 2 628 MWh/year

Power supply from traction system

  • For signalling equipment. - 280 MWh/year and 525 MWh/year
  • For electric switch heating - 42 MWh/year and 29 MWh/year
  • For pre-heating equipment - 7850 MWh/year and 0 MWh/year

Heat requirement

  • Central heating - 12980 GJ/year and 9 630 GJ/year
  • Heating TUV - 10000 GJ/year and 8 540 GJ/year
  • Air conditioning - 260 GJ/year and 260 GJ/year

Other energy

  • Natural gas consumption - 865 000 m3/year and 306970 m3/year
  • Drinking water - 70620,2 m3/year and 25 568,3 m3/year