Světec,SPS Bílina II.fáze

Project number: CZ.04.1.41/0.0/0.0/16_006/0000028
Project location: Ústí nad Labem Region
The exact place of realization: Teplice
Project start date: 16. November 2015
Project completion date: 20. July 2017
EU financial resources: Evropské strukturální investiční fondy (ESIF)
Approved Project total cost: 365 063 444 Kč
Approved EU contribution: 263 793 173 Kč
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Date of project financing decision: 21. November 2016
Project approved by: ŘO OP Doprava
Project approved within the priority axis: 1
Specific objective: 1.1