Reconstruction of railway track no. 2 between km 30,650-38,616 on railway line Havlíčkův Brod – Okrouhlice

Project number: CZ.1.01/1.1.00/07.0018
The exact place of realization: NUTS 5: Tišnov, spadá pod Brno - venkov
Project start date: 1. September 2007
Project completion date: 31. January 2008
EU financial resources: Cohesion fund
Approved Project total cost: 111 466 785 Kč
Approved EU contribution: 66 083 880 Kč
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Construction supervision: SŽDC, s.o., Stavební správa Olomouc
Contractor: OHL ŽS, a.s.
Preparatory documentation contractor: Zdeněk Štěpán, MTPKD
Date of project financing decision: 13. March 2008
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions

Reception
Phone:+420 222 335 711
(during working hours Mo-Fr)

  Mail us
More contacts

epodatelna@szdc.cz Copyrigtht © 2009 SŽDC, s.o.