Optimization of railway line České Velenice - Veselí nad Lužnicí, 1st. Phase

Project number: CZ.1.01/1.1.00/08.0095
Project location: Jihočeský kraj
The exact place of realization: České Velenice
Project start date: 13. October 2008
Project completion date: 31. December 2012
EU financial resources: Cohesion fund
Approved Project total cost: 1 035 379 275 Kč
Approved EU contribution: 512 907 314 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Construction supervision: Ing.Jiří Rejda / Jaroslav Svatoň
Contractor: Sdružení České Veleníce (Viamont DSP a.s., Firesta s.r.o.)
Detailed design contractor, author´s supervision: SUDOP Praha a.s.
Preparatory documentation contractor: SUDOP Praha a.s.
Date of project financing decision: 2. June 2009
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions
Reception
Tel.:+420 222 335 911
Theft, Damage, Vandalism
24/7 phone service: +420 725 144 218
Mail us
More contacts

Copyrigtht © 2009 SŽDC, s.o.