Modernization of the Track Veselí nad Lužnicí – Tábor, Part 1, Doubí near Tábor - Tábor Section

Project location: Jihočeský kraj
Corridor: 4
Project start date: 1. December 2006
Project completion date: 31. July 2009
EU financial resources: Cohesion fund
Approved EU contribution: 75 817 137 €
Approved Project total cost: 3 645 400 780 Kč
Approved EU contribution: 1 886 080 182 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Contractor: Sdružení Doubí - Tábor, vedoucí účastník sdružení OHL ŽS, a.s., další účastníci: Subterra, a.s., Viamont DSP a.s.
Date of project financing decision: 19. March 2010
Project approved by: European Commission
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions