GSM-R Břeclav - Přerov - Petrovice u Karviné

Project number: CZ.1.01/1.2.00/08.0064
Project location: Jihomoravský kraj, Olomoucký kraj, Moravskoslezský kraj, Zlínský kraj
Corridor: 2, 3
Project start date: 1. September 2008
Project completion date: 1. January 2010
EU financial resources: Cohesion fund
Approved Project total cost: 493 951 150 Kč
Approved EU contribution: 329 004 400 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Contractor: Kapsch s.r.o.
Date of project financing decision: 27. August 2008
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.2 - Ensuring Interoperability on Existing Railway Lines, Ensuring Compliance with Technical Specifications for Interoperability (TSI), and the Development of Telematics Systems