GSM-R III. koridor

Project number: CZ.1.01/1.2.00/15.0419
Project start date: 11. October 2014
Project completion date: 31. August 2016
Approved Project total cost: 547 401 719 Kč
Approved EU contribution: 358 108 271 Kč
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Date of project financing decision: 22. September 2015
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.2 - Ensuring Interoperability on Existing Railway Lines, Ensuring Compliance with Technical Specifications for Interoperability (TSI), and the Development of Telematics Systems