Reconstruction of railway track no. 1 and 2 between km 224,391-226,018 on railway line Havlíčkův Brod - Okrouhlice

Project number: CZ.1.01/1.1.00/07.0015
Project location: Vysočina
The exact place of realization: Havlíčkův Brod
Corridor: none
Project start date: 1. October 2007
Project completion date: 1. June 2008
EU financial resources: Cohesion fund
Approved Project total cost: 108 116 180 Kč
Approved EU contribution: 73 365 026 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Construction supervision: Pavel Vincenec
Contractor: Viamont DSP a.s.
Detailed design contractor, author´s supervision: Ing. Pavel Bláha, DMC Havlíčkův Brod, s.r.o.
Preparatory documentation contractor: Ing. Pavel Bláha, DMC Havlíčkův Brod, s.r.o.
Date of project financing decision: 14. February 2008
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions