Electrification including pre-electrification adaptations of the railway line Letohrad – Lichkov state border, 1st construction Letohrad (excluded) – Lichkov state border

Project location: Pardubický kraj
Project start date: 15. August 2007
Project completion date: 30. June 2009
EU financial resources: Cohesion fund
Approved EU contribution: 49 653 990 €
Approved Project total cost: 1 913 619 853 Kč
Approved EU contribution: 1 187 773 089 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Date of project financing decision: 21. December 2009
Project approved by: European Commission
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions