Electrification including pre-electrification adaptations of the railway line Letohrad – Lichkov state border, 1st construction Letohrad (excluded) – Lichkov state border
| Project location: | Pardubický kraj |
| Project start date: | 15. August 2007 |
| Project completion date: | 30. June 2009 |
| EU financial resources: | Cohesion fund |
| Approved EU contribution: | 49 653 990 € |
| Approved Project total cost: | 1 913 619 853 Kč |
| Approved EU contribution: | 1 187 773 089 Kč |
| Final beneficiary: | Správa železniční dopravní cesty, státní organizace (SŽDC) |
| National co-financing authority: | Státní fond dopravní infrastruktury (SFDI) |
| Links: | |
| Date of project financing decision: | 21. December 2009 |
| Project approved by: | European Commission |
| Project approved within the priority axis: | 1 - Upgrading the TEN-T Railway Network |
| Intervention area: | 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions |
|