Reconstruction of railway track Nezamyslice-Pivín

The exact place of realization: Nezamyslice (Prostějov)
Corridor: none
Project start date: 20. September 2007
Project completion date: 31. May 2008
EU financial resources: Cohesion fund
Approved Project total cost: 62 124 910 Kč
Approved EU contribution: 41 474 189 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Construction supervision: SŽDC, s.o., Stavební správa Olomouc
Contractor: TOMI-REMOMT a.s.
Preparatory documentation contractor: MORAVIA CONSULT Olomouc a.s.
Date of project financing decision: 10. March 2008
Project approved by: ŘO OP Transport
Project approved within the priority axis: 3 - Upgrading Railway Networks outside of the TEN-T Network
Intervention area: 3.1 - Upgrading and Development of the Railway Network outside of TEN-T