Reconstruction of switchroom 110 kV and transformer 110 kV of traction substation Pečky

Project number: CZ.1.01/1.1.00/10.0195
Project location: Středočeský kraj
The exact place of realization: Pečky
Corridor: 1, 3
Project start date: 30. September 2011
Project completion date: 31. December 2013
EU financial resources: Cohesion fund
Approved Project total cost: 308 158 000 Kč
Approved EU contribution: 192 282 530 Kč
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Construction supervision: SŽDC, s.o., Stavební správa západ
Detailed design contractor, author´s supervision: SUDOP Praha a.s. - HIP Ing. Miroslav Nezkusil
Preparatory documentation contractor: SUDOP Praha a.s.
Date of project financing decision: 25. November 2010
Project approved by: ŘO OP Transport
Project approved within the priority axis: 1 - Upgrading the TEN-T Railway Network
Intervention area: 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions