Reconstruction of the Přerov railway station, Construction 1
| Project number: | CZ.1.01/1.1.00/10.0180 |
| Project location: | Olomouc Region |
| The exact place of realization: | Přerov, Horní Moštěnice |
| Corridor: | 2 |
| Project start date: | 10. September 2009 |
| Project completion date: | 31. August 2015 |
| EU financial resources: | Planned Cohesion Fund co-financing within OP Transport |
| Approved Project total cost: | 4 920 744 421 Kč |
| Approved EU contribution: | 2 935 231 225 Kč |
| Final beneficiary: | Railway Infrastructure Administration, state organisation (RIA) |
| National co-financing authority: | State Fund of Transport Infrastructure (SFTI) |
| Contractor: | Sdružení Přerov "OHL ŽS a.s; EUROVIA CS, a.s.; AŽD Praha s.r.o.) |
| Project approved within the priority axis: | 1 - Upgrading the TEN-T Railway Network |
| Intervention area: | 1.1 - Upgrading and Development of Railway Lines in the TEN-T Network including Railway Junctions |
|