Reconstruction of the railway track Sokolnice - Chrlice, 3rd construction

Project number: 132/2006-430-OPI
The exact place of realization: NUTS II, Jihomoravský kraj
Project start date: 1. September 2006
Project completion date: 1. December 2006
EU financial resources: European regional development fund
Approved Project total cost: 76 714 728 Kč
Approved EU contribution: 46 028 837 Kč
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Construction supervision: Správa železniční dopravní cesty (SŽDC), Stavební správa Olomouc
Contractor: TOMI - REMONT a.s.
Detailed design contractor, author´s supervision: Moravia Consult Olomouc a.s.
Date of project financing decision: 27. December 2006
Project approved by: MA OP Infrastructure
Project approved within the priority:: 1 – Modernisation and development of transport infrastructure of nation-wide importance
Measure: 1.1. - Modernisation of lines of nation-wide importance and of important railway junctions