Studies (planning technical study and preparatory documentation) concerning the construction of the new railway section "Usti nad Orlici - Chocen" and the passage through the railway junction "Usti nad Orlici"

Project number: 2006-CZ-92106-S-S07.65730
Project location: Pardubice Region
Corridor: 1, 3
Project start date: 1. June 2006
Project completion date: 31. December 2008
EU financial resources: Program TEN-T
Approved Project total cost: 3,072,000 €   ( 89,088,000 Kč )
Approved EU contribution: 1,530,000 €   ( 44,370,000 Kč )
Final beneficiary: Railway Infrastructure Administration, state organisation (RIA)
National co-financing authority: State Fund of Transport Infrastructure (SFTI)
Date of project financing decision: 19. December 2006
Project approved by: European Commission
Ref.No. of the decision: K(2006)7095