Studies concerning the modernisation of the railway section Votice -Benesov u Prahy

Project number: 2006-CZ-92107-S
Project location: Středočeský kraj
Corridor: 4
Project start date: 1. September 2006
Project completion date: 30. June 2008
EU financial resources: Program TEN-T
Approved Project total cost: 4,483,000 €   ( 130,007,000 Kč )
Approved EU contribution: 2,200,000 €   ( 63,800,000 Kč )
Final beneficiary: Správa železniční dopravní cesty, státní organizace (SŽDC)
National co-financing authority: Státní fond dopravní infrastruktury (SFDI)
Contractor: SUDOP PRAHA, a.s.
Date of project financing decision: 19. December 2006
Project approved by: European Commission
Ref.No. of the decision: K(2006)7101